Project Description

Project Description

Our design encompassed removing the old damaged components, installing eight new 8-foot diameter drilled piers into bedrock, two new steel towers, lead paint abatement, reusing five existing girder spans, new concrete deck and handrail. A design requirement for the new towers was that the new towers had to visually match the existing towers. COP was responsible for all facets of the project including design, permitting, procurement and construction.

Project Details

LOCATION: Lewistown, Montana
DURATION: 40 weeks
PROJECT TYPES: Highways, Streets, & Bridges & CMGC

Let’s Build America Together Contact Us