This project consisted of installing 1200 lineal feet of 30-inch ductile iron pipe and 100 lineal feet of 42-inch HDPE, dredging of the marina, as well as part of the lake and constructing settling ponds for the dredged material. The project also included 37-foot-deep excavation for a wet well and 25-foot-deep excavation of the 42 inch HDPE.

COP also constructed a new pump station consisting of four new 10 inch pumps with mechanical pipe, including two self-cleaning amiad filters. A new intake structure, with 30-inch SS wire screens and air burst systems, was also installed.

For privacy reasons YouTube needs your permission to be loaded. For more details, please see our Privacy Policy.

Project Details

LOCATION: Saratoga Springs, Utah
DURATION: 48 weeks
PROJECT TYPES: Treatment Plants & Pump Stations