Project Description

Project Description

The Davis Lane Lift Station and Norton East Ranch Outfall Sewer Project consisted of the construction of a 20 foot x 45 foot lift station with metering building. The lift station required an excavation depth of 35 feet which was all self-performed by COP. COP installed 11,000 lineal feet of 27-inch and 30-inch gravity sewer main to the lift station with a 700 lineal foot 64-inch micro tunnel underneath I-90, Montana Rail Link tracks and two frontage roads. The project also consisted of 3,800 lineal feet of dual 18-inch force mains to bring sewage from the new lift station to the existing sewer plant.

Project Details

LOCATION: Bozeman, Montana
DURATION: 56 weeks
PROJECT TYPES: Underground Utilities

Unique Problem Solved

This project was unique in that it required a large excavation, which COP dewatered and shored, to install the new lift station.